Canyon Road East - 208th Street East to 200th Street East (CRP 5764)

What's Happening


Engineering: We have completed preliminary engineering for the revised project limits of 208th Street East to 200th Street East. The project is now in the final engineering phase, which includes finalizing details for all construction elements and preparing contract documents.

Land: Right-of-way plans were finalized in July 2020. Right-of-way agents are in the process of making contact with property owners.
Image of the project vicinity map.
Image of the road project before construction.

About the Project


Planned improvements to continue widening Canyon Road East from 208th Street East to 200th Street East (CRP 5764) are intended to increase transportation connectivity, and include:
  • Extending Canyon Road East from 200th Street East to 208th Street East.
  • Constructing concrete curb, gutter and sidewalk on the west side.
  • Constructing an enclosed storm drainage system, stormwater treatment and storage facilities.
  • Providing two through lanes (one in each direction)
  • Constructing a new traffic signal at the intersection of 208th Street East.
  • Modifying the existing signal system at 200th Street East.
  • Constructing roadway illumination.
Image of the proposed roadway section.

Project Timeline


August 2020: Transition into the final engineering phase. Work begins on the right-of-way acquisition process and the finalization of the construction plans, specifications, and estimate.

December 2021: Advertise for construction bids.

Spring 2022: Construction expected to start.

Approved Right-of-Way Plans - 208th St E to 200 St E

Image of the project right-of-way plan cover sheet.

Approved Right-of-Way Plans - 192nd St E to 224th St E

Image of the project right-of-way plan cover sheet.